Al-Zour LNG Import Terminal

Al-Zour LNG Import Terminal

The Al-Zour LNG Import Terminal is the world’s largest liquefied natural gas (LNG) import terminal, located 90 kilometers southeast of Kuwait’s capital. The project included the construction of a re-gasification facility, eight LNG storage tanks with a capacity of 225,000m³ each, marine facilities including two marine jetties, and berthing facilities for loading, and other components such as 14 HP pumps, boil-off gas (BOG) and flare facilities.

The facility was expected to produce approximately 22 million metric tonnes (MMT) of natural gas a year and would have a storage capacity of 1.8 million m³ of LNG. The liquefaction capacity of the terminal would be 30 billion cubic metres a day (bcm/d).

Dextra supplied 202 tons of grade 700 marine tie bars and 166 tons of wailing beams for the construction of marine facilities of this project. Tie bars were used as anchors between sheet piles or concrete walls.

The import terminal was completed in November 2021 and it reached full operations in February 2022. The LNG terminal is providing the Middle East country with a stable gas network in the long run, allowing it to respond to the rising call for energy diversification and sustainable energy.

Image credit: Hyundai Engineering Co.

Santo Antônio Hydroelectric

Santo Antônio Hydroelectric

Santo Antônio Dam is a hydroelectric dam set up on the Mareira River, in the state of Rondônia, Brazil. The dam is powered by 50 turbines for a total capacity of 3,580 MW.

For this major dam project, Dextra Do Brasil delivered to contractors Odebrecht & Andrade Gutierrezits its Rolltec rebar coupler solution.

Rolltec is the most popular rebar slicing solution in Brazil, providing a competitive alternative to lap splices. The rebar preparation is supported by a unique light equipment, operated by a single operator. The Rolltec machine is relatively easy to transport and convenient to install even on most remote locations such as dam construction sites.

On the Santo Antonio dam, rebar coupler were used to reconnect bent rebar. To do so, a straight bar is previously threaded (A/B/C thread length). The bar is then bent according to project requirements.

If needed, to protect the thread coupler can be temporarily set up onto the rebar as well.

Please consult us for more technical information about coupler applications on bent bars.

Maitree Super Thermal Power Project

Maitree Super Thermal Power Project

Maitree Super Thermal Power Project is a 2×660 MW coal-fired power station project being developed by the Bangladesh-India Friendship Power Company (BIFPCL), a 50-50 joint project of the governments of Bangladesh and India. The power station will be located in Rampal, Bangladesh.

For this project, Dextra has supplied more than 400 assemblies of grade 700 Marine Tie Bar systems to connect piles and waling beams for a 1.2km long jetty of the coal power plant.

Dextra’s Marine Tie Bar systems consist of steel bars and anchorage accessories that act as an anchorage to tie back sea walls to anchor walls.

Bars are available in three carbon steel grades, up to a yield stress of 700Mpa and can be chosen among a selection of 24 bar diameters, up to M162, allowing a perfect match to the performance requirements.

In addition, standard range of anchorage components allow easy installation and connection to all kinds of marine walls.

The construction of the Maitree Super Thermal Power started in 2017 and is planned to be finalized by 2022.

Bakheng Water Treatment Plant

Bakheng Water Treatment Plant

The Bakheng Water Treatment Plant is located in the Bakheng district of Phnom Penh, Cambodia. The plant will be built to improve the water supply in this area and eventually give a 60 percent increase in drinking water delivery capacity due to substantial urban expansion.

A drinking water treatment plant and transfer pipelines are part of the project. The supply system will eventually provide drinking water to more than 1.5 million residents in Phnom Penh’s north-east.

By the end of Phase 1, the plant should be operational to provide drinking water to the more than 750,000 inhabitants of the area. By the end of Phase 2, its capacity will be doubled.

The project includes earthworks and soil treatment, civil engineering design of the structures, equipment installation, power supply to the equipment, and system automation.

Dextra supplied Glass Fiber Reinforced Polymer (GFRP) rebars which were installed in bored piles instead of reinforcement of traditional steel rebars to facilitate the TMB breakthrough in the underground waterway tunnel.

Karimun Yard

Karimun Yard

The Karimun Yard located on the small island of Karimun (pop. 200,000), less than 25km away from the island of Batam (Indonesia) and Singapore. The Karimun Yard, operated by Saipem offers more than 780,000 sqm* of fabrication areas with an annual production of 50,000 tons.

Between 2009 and 2010 Dextra has manufactured and supplied for Saipem large >Marine Tie Bars, which were incorporated into the main quay wall. In 2008, Dextra also supplied the Marine Tie Bars and >Waling Beams connecting the sheet pile walls of the service jetty

For the main yard, Dextra supplied its Marine Tie Bars Grade 700, which is the highest in the range. Higher tie bars grades allow to high performance while limiting the size and weight of the bars, making them easier to transport and install. Grade 700 can also be used to optimize design, for example by spreading the bars further away from each other, hence reducing the total number of bars on the project.

To connect the bars to the walls, ball cages were used. Used together with a bearing plate embedded in wall, ball cages allow a multidirectional adjustment angle of 10°. To splice bar segments, couplers were also used.

For more information about our marine solutions in Asia Pacific, please consult our Bangkok

*CF Saipem Yard Sheet 07.2014

Reventazón Hydroelectric Dam

Reventazón Hydroelectric Dam

Reventazón Dam is a concrete-face rock-fill dam set up on the Reventazón River, in the Limon province of Costa Rica. The dam, inaugurated end of 2016, is the largest power station in the country with a total power capacity of 305MW. The project has become a model in term of environmental integration, featuring passages for animals.

For this major dam project, Dextra Latin America continuously delivered and supported contractor ICE from 2010 to 2016. Dextra supplied its Rolltec rebar splicing solution, couplers and machine. Rolltec is the most popular rebar slicing solution in Latin America, providing a competitive alternative to lap splices.

The rebar preparation is supported by a unique light equipment, operated by a single operator. The Rolltec machine is relatively easy to transport and convenient to install even on most remote locations such as dam construction sites.

Rolltec splices were used inside the water tunnels, installed on bent rebar. For that kind of application, the straight bar has to be threaded, then bended. During the bending operation, a coupler may be temporarily fit onto the bar end in order to protect the thread.Rolltec splices were used inside the water tunnels, installed on bent rebar. For that kind of application, the straight bar has to be threaded, then bended. During the bending operation, a coupler may be temporarily fit onto the bar end in order to protect the thread.

Dextra Rolltec couplers were also installed into the tall structure (130m high) as a way to splice rebar vertically.

Hyosung LPG Cavern

Hyosung LPG Cavern

This multi-phase project handled by Hyosung Group will include a propane dehydrogenation (PDH) production plant, a polypropylene (PP) plant, a liquefied petroleum gas (LPG) storage tank, and warehouses for LPG and petrochemical products.

The whole complex will cover 60 hectares of the Cai Mep Industrial Zone in Ba Ria-Vung Tau, located near Ho Chi Minh City.

Dextra is supporting the construction of the 240,000-ton LPG underground storage facility by supplying 30,000 units of glass fiber reinforced polymer (GFRP) rock bolts to consolidate the cavern rock face around the 150m deep excavation area.

Injecting sea water inside the rocks around the cavern will create a water curtain that will effectively prevent any oil leakage: in this high corrosive environment, GFRP is the ideal solution.

Dextra GFRP Rock Bolts are cuttable mining anchors based on fully threaded GFRP tendons. The bolts are available in 7 diameters from 20mm to 40mm, delivered with GFRP plate and nuts. Due to GFRP’s lightweight nature, it is easy to handle, transport and installation inside the tunnel.

The facilities are expected to begin commercial operation in 2020.

Visakh Refinery Modernisation

Visakh Refinery Modernisation

Visakh Refinery Modernisation Project is a brownfield expansion of the Visakh refinery located in Visakhapatnam, India.

The project will expand the refining capacity from 8.3MMTPA (millions of metric tonnes per annum) to 15MMTPA, while enabling the production and distribution of the fuels that comply with Bharat Stage-VI, a new emission standard instituted by the Government of India.

Dextra was involved in the expansion by supplying Unitec bolted couplers for precast beam connections.

Unitec is a bolted splicing system designed for the connection of two rebars with no thread: its screws will lock both bar ends and complete the connection.

The Visakh Refinery Modernisation project is scheduled for completion in 2020.

Sellafield decommissioning

Sellafield decommissioning

Sellafield is a now decommissioned nuclear plant site specialized in the fuel reprocessing and decommissioning of others UK and international reactors. It is located in Cumbria, in the North West of England.

Dextra has been involved in supplying rebar connection solution for the construction of new buildings in 2008 through its local rebar fabricator partner in the UK.

Griptec was the preferred rebar splicing solution as it’s if certified TA1-A, TA1-B and TA1-C (“Sellafield” certification level), the three main levels of rebar splice certifications by CARES.

Griptec features an unmatched performance level and an automatic testing process which systematically tests all the connections produced as part of its standard cycle: a guarantee that 100% of the connections perform above the project requirement.

More than 80,000 Griptec connections have been used on the project, mostly for wall applications.

La Hague nuclear waste reprocessing plant – the interim storage

La Hague nuclear waste reprocessing plant – the interim storage

La Hague site is a nuclear fuel reprocessing facilities located in La Hague, northern France. The plant has been treating spent nuclear waste from several countries since 1960s. Nowadays, Being operated by AREVA NC, it now operates nearly half of the world’s spent nuclear fuel recycling and reprocessing capacity, including waste from France itself, as well as from Japan, Germany, Belgium, Switzerland, Italy, Australia, Spain and the Netherlands.
The reprocessing plant also separates waste of different radioactive activity and life span, and applies specific storage solutions to each type of waste. Therefore, in order to reassure the reinforcement of the plant’s two recent nuclear waste storage, the main contractor VINCI – Travaux Public Cherbourg opted for Dextra’s 100%-proofed splicing system Griptec, delivered through its local fabricators in France.

Griptec, full performance rebar couplers for nuclear projects worldwide

For the construction of nuclear projects, full-performance reinforcement solutions are required. This is the reason why Dextra Griptec was preferred for this project, as it is also certified AFCEN, the international standard for nuclear plants. More than 5,000 tons of Dextra products were delivered on-site for the construction of two storage buildings, both intended to store Uranium and Plutonium.
Griptec couplers are used to reinforce the storages’ walls, as it is a full-performance (tension, compression, cyclic and fatigue) rebar splicing system. The solution provides no place for error, as each and every connection is systematically proof-tested by pull test during extrusion cycle as part of its standard cycle, and can perform above the project requirement. Moreover, for our customers in nuclear industry, Dextra provides more than only reinforcement solutions: we also accompany designers, consultants and contractors through each step of their construction project.

 

For more information about our solutions available in France and Europe, please contact our Paris office.

Please enter your information

Contact us

   Share your information with us and we’ll get back to you as soon as possible.