Green Duba統合型太陽光複合サイクル発電所
Duba ISCC Green Power Plant 1 is a large power infrastructure project located in the northwest of Saudi Arabia, along the Red Sea. The ISCC (Integrated Solar Combined Cycle) technology adds 50 MW of solar power to the gas and steam turbines, generating a total of 500 MW of electricity.
For this project, Dextra supplied Double Corrosion Protection Ground Anchors, used as a permanent anchoring solution for the excavation work preparing the pumping chamber. A total of 264 anchors (Grade 1080/1230, Ø32 & 40 mm) were supplied and installed across four layers.
の Double Corrosion Protection anchors supplied for this project were pre-grouted at the Dextra factory, applying the first layer of grout between the steel bar and HDPE sleeve. The pre-grouted segments were reconnected on-site using couplers. Pre-grouted anchors not only save time and reduce costs during on-site operations, but they also enhance overall anchor quality by ensuring that the first grout layer is applied in a factory-controlled environment.
現場での設置は基礎請負業者 BAUER によって行われ、掘削、吊り上げ、設置、グラウト注入、ポストテンション作業が行われました。デエクストラは、地質工学の専門家のチームを現場に派遣して、設置の初期段階で指導を提供しました。
インストールの一般的な順序は次のとおりです (下の図に示されています)。
- 出荷ラックから開梱した後、熱収縮スリーブで覆われたカプラーでセグメントを接合します。
- 組み立てられたアンカーの組立て現場から吊り上げエリアまでの輸送 (リニア メートルあたり 13kg)。
- 降下を制御するためのアンカーの頭部にケーブルを配線します。グラウトパイプもアンカーに沿って事前に設置されています。
- 30メートルのアンカーをグラウトパイプとともに掘削穴に挿入します。
- グラウト注入と応力注入後、グリースを充填したヘッド キャップをアンカー ヘッドに取り付け、アンカーを腐食性の外部環境から完全に隔離します。
中東における当社の掘削および地盤ソリューションの詳細については、当社までお問い合わせください。 ドバイオフィス.