ブリュッセル地下鉄3号線
ブリュッセル メトロは、ベルギーの首都ブリュッセルの大部分を運行する高速交通システムです。従来の地下鉄 4 路線と地下鉄以前の 3 路線で構成されています。
Line 3 is a tram line that runs through the city center from Churchill in the south to Esplanade in the north, using the North-South Axis tunnel. The total route will be 10.3km long.
An 150m long new tunnel was dug underneath the Brussels North railway station to connect two existing underground tunnels. It was an important component of the new metro link.
Dextra supplied ソニテック, a tube solution that facilitates the integrity testing of foundations using the CSL testing method, to the construction site of Line 3. 13 kilometers of the tubes were installed in the 18m long pile cages.
の ソニテック system has been designed with the sole purpose of being easy to assemble and install in reinforcement cages.