Cairo Metro is the rapid transit system in Greater Cairo, Egypt. It was the first of three full-fledged metro systems built in Africa, as well as the first in the Arab world.
The system currently has 74 stations, 3 of which are transfer stations, with a total length of 89.4 kilometers. There are 3 operating lines in the system, numbered from 1 to 3.
Cairo Metro Line 4 will be built as a new underground line that will help to alleviate traffic congestion. Phase 1 will run for 19 kilometers and include 16 stops, connecting the heart of Greater Cairo to Giza’s pyramids.
Dextra has supplied turn-key solutions for the reinforcement of the diaphragm walls.
- 450,000 Bartec+ couplers
- 42 GFRP soft-eyes
It is projected to be Egypt’s major tourist transportation line, with service up to the Pyramids area beginning in 2024.
GFRP Connector
for insulated precast sandwich panels
Suitable for composite, partially composite and non-composite precast concrete sandwich panels.
Manufactured with optimum bonding with concrete thanks to dual surface deformation and sand coating.
Stronger than steel, therefore fewer number of ties are needed compared to other methods.
Lighter than other connectors and easier to install, leading to higher sandwich panels productivity.
Made of corrosion-resistant material: GFRP (Glass Fiber Reinforced Polymer) leading to slimmer panels.
More about our latest projects
Kursk II Nuclear Power Plant, Russia
Bartec standard and transition couplers, and headed bars, were installed in the reactor buildings.
Queensland Curtis LNG (QCLNG), Australia
307 tons of marine tie bars serve as an anchorage for the marine offloading facility’s anchor walls.
Reconstruction of Pak Kok Pier, Hong Kong
Dextra delivered over 600m of GFRP rebars in straight and bending shapes for the reinforcement of the ferry pier.
Fully-threaded bar tools available for download!
Le système de barre de post-tension Dextra (barre PT) se compose d'une barre en acier à haute résistance ainsi que d'accessoires, tels que des coupleurs, des rondelles d'écrous, des plaques d'appui.
Des barres lisses et entièrement filetées sont disponibles pour s'adapter au mieux à l'application du projet, qu'il s'agisse de travaux temporaires ou permanents.
Les barres entièrement filetées sont désormais livrées avec des outils pour AutoCAD, Revit et Tekla pour faciliter la conception et le détail des structures en important les composants dans le logiciel.
WEBINAR RECAP:
Requirement of Rebar Coupler as per ISO 15835
Dextra shared its knowledge on coupler standard compliance in Malaysia and around the world in the latest webinar: “Requirement and Application Solutions of Dextra Rebar Coupler as per ISO 15835 In Compliance to CIDB Schedule 4 Order 2021”, organized by the Master Builders Association Malaysia, on November 29, 2021.
Dextra Group fait un don au fonds de secours COVID-19 en Inde
Dextra Group donated INR 15 Lakhs (20,000 US$), which was converted from the running distance of our charity virtual run event, to Dr. Sudin Gaikwad, the Deputy Secretary of the Maharashtra Chief Minister’s Relief Fund for COVID-19 in India in October 2021.