Presa de Belo Monte
The Belo Monte Dam is a hydroelectric dam built on the Xingu River in the state of Pará, northern Brazil. Upon its inauguration, it will become the second-largest dam in Brazil and the fourth-largest in the world, with a total maximum capacity of 11,233 MW.
For this major dam project, Dextra Do Brasil continuously delivered to contractors its Empalme mecánico de barras de refuerzo Rolltec solución entre 2011 y 2016.
Rolltec is the most popular rebar splicing solution in Brazil, offering a competitive alternative to lap splices.
A total of 250,000 couplers have been used in the Belo Monte Dam, incorporated across all parts of the structure.
Rebar preparation is supported by a unique lightweight machine, which can be operated by a single person.
The Rolltec machine is relatively easy to transport and convenient to install, even in remote locations such as dam construction sites.