Taishan EPRs 1 und 2
Taishan EPRs are two nuclear reactors of the EPR type, each with a capacity of 1,750 MW, built by Areva and located near Taishan in Guangdong province, China.
Dextra was present on-site from the beginning of construction in 2009 until 2016. Reactor operations were planned to start in 2017.
For this challenging project, Dextra supplied its Griptec rebar splicing solution, which was used in the concrete structure of the reactor.
The Bartec rebar coupler solution, as well as Headed Bars, was also used in other buildings of the project.