محطة ضباء الخضراء المتكاملة لتوليد الطاقة الشمسية بالدورة المركبة
Duba ISCC Green Power Plant 1 is a large power infrastructure project located in the northwest of Saudi Arabia, along the Red Sea. The ISCC (Integrated Solar Combined Cycle) technology adds 50 MW of solar power to the gas and steam turbines, generating a total of 500 MW of electricity.
For this project, Dextra supplied Double Corrosion Protection Ground Anchors, used as a permanent anchoring solution for the excavation work preparing the pumping chamber. A total of 264 anchors (Grade 1080/1230, Ø32 & 40 mm) were supplied and installed across four layers.
ال Double Corrosion Protection anchors supplied for this project were pre-grouted at the Dextra factory, applying the first layer of grout between the steel bar and HDPE sleeve. The pre-grouted segments were reconnected on-site using couplers. Pre-grouted anchors not only save time and reduce costs during on-site operations, but they also enhance overall anchor quality by ensuring that the first grout layer is applied in a factory-controlled environment.
تم تنفيذ التثبيت في الموقع من قبل مقاول الأساس BAUER، الذي أجرى عمليات الحفر والرفع والتركيب والحشو وعمليات ما بعد الشد. قدمت Dextra التوجيه خلال الخطوات الأولى للتركيب من خلال إرسال فريق من المتخصصين الجيوتقنيين إلى الموقع.
التسلسل العام للتثبيت هو كما يلي (موضح في الصور أدناه):
- بعد التفريغ من رفوف الشحن، يتم ربط الأجزاء باستخدام قارنات التوصيل، وتغطيتها بأكمام قابلة للانكماش الحراري.
- نقل المرساة المجمعة من التجميع إلى الموقع إلى منطقة الرفع (13 كجم لكل متر طولي).
- كابل توصيل على رأس المرساة للتحكم في الهبوط. يتم أيضًا تثبيت أنبوب الحشو مسبقًا على طول المرساة.
- إدخال مرساة بطول 30 مترًا في الحفرة المحفورة مع أنبوب الحشو.
- بعد الحشو والإجهاد، يتم تثبيت غطاء رأس مملوء بالشحم على رأس المرساة، للحفاظ على المرساة معزولة تمامًا عن البيئة الخارجية المسببة للتآكل.
لمزيد من المعلومات حول حلول الحفر والأرضيات التي نقدمها في الشرق الأوسط، يرجى الاتصال بنا مكتب دبي.